Digging a rain canal for Molham camp …
Following up the rain canal works….
concrete pouring of the canal walls
After completing the construction of the canal walls, starting pouring the roof of the canal
The drilling of the rain canal project, consisting of three stages, has been completed at the Molham camp:
First stage: drilling the canal
Second stage:concrete pouring of the canal walls
Third stage: concrete pouring of the canal roof
Starting date: 25/07/2020
implementation duration: 53 days
Project completion and delivery date: 16.09.2020
Project supervision committee:
Ihsan Relief and Development