The toilet blocks were supplied and installed in the following sites:
Sheikh Mustafa Camp (edlib-Harbnoş)
Al-Rashid camp (Aleppo – Samaan Mountain)
El andalusia camp (edlib-Zardana)
Al-Muthanna camp (edlib-Harem-Al-Dana-Tal Al-Karama)
Al-Kaibiya Camp (edlib-Harem-Dana-Kafardaryan)
Starting date: 09/07/2020
Implementation duration:20 days
Project supervision committee:
Ihsan Relief and Development
The project was completed and delivered on 29/07/2020.