PROVODING 100 KVA DIESEL GENERATOR AND 18 KW MULTI-STAGE CENTRIFUGAL PUMP IN (Al Jabal Camp)
Jabal camp project / Jarablus … Generator, electrical panels and vertical pumps … Starting date: 07/08/2020 Duration of application: 30 days Project supervision committee: IYD Humanitarian Relief Foundation The project was completed and delivered on... لـ DeltaT | 01/07/2020 | Completed work
STONE FLOOR PROJECT (MOLHAM CAMP)
Project of gravel lying of Mulham Camp gravel lying of Mulham Camp Start Date: 01/07/2020 Implementation duration: 10 days Project supervision committee: Ihsan Relief and Development The project was completed and handed over on... لـ DeltaT | 01/07/2020 | Completed work
STONE FLOOR PROJECT (EHTIMLAT CAMP)
Spreading stones in Azaz import camp starting date: 01/07/2020 application period: 10 days Project supervision committee: Ihsan Relief and Development Infrastructure building works in ehtemlat camp …. Project supervision committee: Ihsan Relief and Development The... لـ DeltaT | 29/06/2020 | Completed work
PROJECT OF PROVIDING AND IMPLEMENTATION SANITATION NETWORK AND SEPTIC TANKS IN MOLHAM CAMP
Establishing a sewage network in the Azaz-Akhtarin-Jarablus area (Molham camp). Providing and implementing a sewage network and septic tanks Start Date: 06/29/2020 Implementation duration: 18 days Project supervision committee: IYD Humanitarian Relief Foundation...Recent Posts
- Kafr Rouhin Wastewater Treatment Plant
- Establishment of the main sewer line and connecting the camps to the main sewer line in Idlib
- Implementing a high water tank and installing a water and sanitation network in the camps in Afrin and Jandires
- Installation of 2000 liter polyethylene water tanks in Idlib
- Rehabilitation of the sewage network in Azaz and Al-Bab